In 2009, we dug this crane out of the side of a sand quarry in Florida, shipped it out to Long Beach, CA. on 13 trucks, then began the entire rebuild.
Project Facts
• The rebuild was completed in 4 months
• New custom house
• New machinery including a Caterpillar C18 ACERT and all new systems
• New cab with electronic over air controls
• Sheet metal house was replaced with a fabricated steel house
• All the work was done in-house by Curtin Maritime
• Every inch of the crane was disassembled, sandblasted and painted
• All new turning components including bushings, bearings, swing circle house rollers, hook rollers, and stump.
Every inch of the crane was disassembled, sandblasted, and painted, then put back together with all new turning components including bushings, bearings, swing circle house rollers, hook rollers, and stump.

We selected this crane because we could use the robust and proven reliability of a Lima 2400, combined with modern technology to make a digging machine unparalleled by others in its class.

The rebuild was completed in 4 months and involved a new custom house with brand new machinery including a Caterpillar C18 ACERT and all new systems, as well as a new cab with electronic over air controls to lessen the burden of continuous operating for our Leverman.

The sheet metal house was replaced with a fabricated steel house that is more conducive to the marine environment, and quieter for the crews working on the deck around it. All the work was done in-house by Curtin Maritime.

Location
Port of Long Beach, Long Beach, Ca, Map >
Client
In-House Project
Categories
Design-Build, Engineering, Fabrication
Contact Info
Services
Design-Build, Vessel Fabrication
Related Projects
US Navy Ramp Fabrication & Installation
US Navy Ramp Fabrication & Installation
NRG Intake Forebay Structure Demolition Project
Removing a structure that is subsea in order to widen the channel for ships to pass through safely. What that entails is the removal of approximately 4000 tons of concrete to depths of up to 52 feet.
Vessel Design Build Fabrication – Tugboat Bernardine C
In 2015 we completed our first "ground-up" vessel fabrication build, the Bernardine C. Built here at our yard in the Port of Long Beach, CA. The tugboat is Tier III compliant.